Environment & Social

EIA study for 2x 20MW Sagana Hydro Power Project

KTL was awarded a contract to undertake the Environmental Impact assessment study for the proposed project in accordance with EMCA and IFC’s Environmental and Social Performance Standards.

The proposed Project comprises of a 140m long weir, 4.6km water tunnel Valve Chamber, 1.9m Twin steel Penstocks, 2 Power Houses (20 mw each), Power Switch yard; High Power Transmission line (Approximately 7km to Kibirigwi, Kirinyaga County).

The assignment is on-gong and  include Aquatic and terrestrial ecological studies, hydrological and geological studies, Social Impact Assessment and development of stakeholder engagement plan.